MOT Type 1 Calculator

Work out how much Type 1 sub-base you need for an area.

Volume

4.5m³

Estimated weight
9 tonnes

Weight assumes compacted MOT Type 1 at about 2.0 tonnes per cubic metre.

v1.0 · Reviewed September 2026

How this is worked out

Volume is area × compacted depth, converted to tonnes at 2.0 tonnes per cubic metre for compacted MOT Type 1.

Worked example

  • Area 30 m²
  • Compacted depth 150 mm

30 × 0.15 = 4.5 m³, and 4.5 × 2 = 9 tonnes

4.5 m³, weighing about 9 tonnes

Assumptions and limits

  • Type 1 loses roughly a quarter of its loose depth when compacted, so lay in layers and allow extra loose material.
  • Typical depths are around 100 mm for footpaths and 150 mm or more for drives, but that depends on the ground and the loading.